Friday, September 28, 2007

The basement is sealed and the perimeter drains are in.


The crushed stone is added to the basement prior to the radiant heat tubing and the concrete pour

The lull arrives today in anticipation of the house delivery monday morning from Connor Homes.
Posted by Picasa

Tuesday, September 25, 2007


View of the house and lot from the driveway
Posted by Picasa
Sept 25th. Looking at the garage entrance

Looking from the rear of the master toward barn

Same view

View of the barn from the future rear deck
Posted by Picasa

Thursday, September 20, 2007


Wednesday 9/18...The main foundation is done and the footings for the garage and bedroom are in. Ran out of batteries thus no more picts.
Posted by Picasa

Tuesday, September 18, 2007

Tuesday Sept 18th: The basement walls are being poured on another glorious Freedom day.

Posted by Picasa
Day 5: The footings are poured.

Posted by Picasa
Day 4: The cellar hole is dug
Posted by Picasa
Day 3: The barn addition comes down to make room for the driveway.


Posted by Picasa
Supervising Day one. Charlie and his sidekick.

The excavator makes short work of the trees on site.

Our first lawn ornament
Posted by Picasa

Our Freedom Home Project



The pastoral scene before the excavator arrives
Posted by Picasa